Run permits through the day

The live board, entry logs, extensions, handovers and closure — the operational side of permit control.

6 min read · Last reviewed 18 August 2026

Watch the board

  • Permits → Board shows every open permit: status, site, type and clock, at a glance.

  • It is the 8am answer to “what high-risk work is running right now?” — and the 4pm answer to “what should have closed by now?”.

Log entries and exits

  1. 1

    For confined-space work, log every entry and exit against the permit as they happen.

  2. 2

    The permit always knows who is inside — and refuses to close while anyone still is.

Extend and hand over properly

  1. 1

    Extending a permit re-checks the clashes — the welding that was fine this morning may not be fine now that another crew started downstairs.

  2. 2

    Resuming suspended work needs a real attestation and a fresh, in-range gas re-test — not a nod.

  3. 3

    Handover transfers the permit to a new acceptor; it can never target the authoriser, because the person who authorised the work cannot also be the person doing it.

Expiry and closure

  • An hour before expiry, the people responsible are warned; once a permit lapses without closure, it escalates. The watch runs every 15 minutes.

  • Closure records the end of the work; the permit PDF — signed, timestamped in the site’s own timezone — is ready for the job file.

Tip: Treat the expiry warning as a planning tool: extend deliberately before the window lapses, rather than explaining afterwards why work continued on a dead permit.

About this modulePermits to workAuthorise high-risk work with the checks that must happen first — and a live board of what is open right now.